RECENT PROJECTS
Heathrow Bravo Works
CLIENT: Ferrovial
PROJECT VALUE: £1,600,000
PROGRAMME: 78 weeks
MAIN WORK STREAMS
Reinstatement of taxiways after new fuel pipes placed
Block paving
Tarmac planning
Supply of top soil
Supply of trucks for concrete works
Ferry Lane
CLIENT: CBRE
PROJECT VALUE: £750,000
PROGRAMME: 14 weeks
MAIN WORK STREAMS
Demolition of 9 warehouse units
Remediation of waste products and removal of Japanese knotweed
Heathrow T2 Car Park
CLIENT: Laing O’Rourke
PROJECT VALUE: £900,000
PROGRAMME: 36 weeks
MAIN WORK STREAMS
Removal of concrete and tarmac on top level of car park
Diamond core drilling and saw cutting
Selco Builders Merchants
CLIENT: Selco Builders Merchants
PROJECT VALUE: £500,000
PROGRAMME: 24 weeks
MAIN WORK STREAMS
Demolition and extension of existing warehouse.
Concrete bases, concrete road, tarmac and cladding
Langley Farm
CLIENT: The Princesses Trust
PROJECT VALUE: £150,000
PROGRAMME: 6 weeks
MAIN WORK STREAMS
Removal of old road and pour new cobble effect concrete.
Demolition of old sheds and parlours.
Hanson Aggregates
CLIENT: Hanson Aggregates
PROJECT VALUE: £350,000
PROGRAMME: 14 weeks
MAIN WORK STREAMS
Construction of new Tarmac batching plant in a quarry in Pontypridd Wales.
Concrete bases, concrete road to the offices and aggregate stores.
Heathrow T2B
CLIENT: Balfour Beatty
PROJECT VALUE: £100,000
PROGRAMME: 3 weeks
MAIN WORK STREAMS
Removal of Tarmac and concrete road.
New waterproofing to basement.
Reinstate tarmac.